Decisions

Decision logs: what was decided, and when it was needed

The GC's RFI log shows what the design team owes. Nobody's log shows what the owner owes. Keep that list yourself, with a name and the date the field needs the answer.


First shared on LinkedIn on November 12, 2026. Read the original post.

Final paint colors. Card reader locations. Whether the break room gets a sink. Whether the second IDF closet gets generator power.

None of those are RFIs. They come up at the OAC. Someone on the owner's side says "let me check with the user group." Then they live in somebody's inbox.

The GC's look-ahead shows ceiling close-in on level 2 on the 20th. Card reader rough-in has to be in before the lid goes on. Nobody decided. The GC sends a delay notice and points at the minutes. They are right.

Keep the owner's side of the scoreboard

The owner's PM keeps a decision log. It is not the RFI log, and it is not the action register, though the three talk to each other. Each line on the decision log has four parts.

  • What is being decided. A choice, written so a later reader can tell what the options were. "Finish selection" is too loose. "Break-room paint, color A or color B, including the accent wall" can be closed.
  • Who on the owner's team decides. One person. If the user group has to be consulted, that is part of the work, but one name still owns the decision.
  • The date the field needs it. Taken from the look-ahead, not from "soon." This is the date that makes the line urgent, or not.
  • The date it was made, and what was decided. When it closes, write the answer and the day. A decision with no date of record will get relitigated.

If the owner still has to choose, the choice stays on the open list with a name and a date. It does not leave the room as a maybe.

Put decisions at the top of the meeting

A typical agenda buries the choice. Safety, schedule, cost, RFIs, then every trade gets a turn. The decision you needed is item 9 of 12. At minute 55, the architect is already packing up. Someone says "let's take that offline." The owner's rep walks out with nothing decided.

Flip it. Open with last week's open actions. Then the decisions that need an answer today. Each one gets a name, what is being decided, and the date it was needed. Updates come after. If an update does not need a decision or a date, it goes in the report, not the room.

Send that agenda the Friday before, with the names of who has to be in the room. People cannot decide if they are not there.

Write the decision when it is made

An open log is only half the tool. When the owner chooses, close the line the same day. Write what was decided, who decided it, and the date it takes effect. If the choice is "color B, and the accent wall matches the corridor," write that, not "finishes approved." Someone will ask in two months what was approved, and the log should answer without a hunt through email.

Email is not the log. A decision that lives in a thread with eight people will be restated, softened, or forgotten. Minutes are not the log either, though they should point to it. The log is the standing record: open decisions with a field-need date, and closed decisions with a date of record.

If a closed decision gets reopened, do not erase the first one. Add a new line that says what changed, who changed it, and the new field-need date. The history is part of the value. It shows the owner what already got decided when a user group tries to reopen a color that has already been released to the painter.

Monday move

Go through the last four weeks of minutes. Pull every "owner to confirm" and "owner to advise" into one list. Put a field-need date next to each one from the look-ahead. Anything due inside two weeks goes to the decision-maker this week, by name.

The free Meeting Pack includes a decision log built for this: what was decided, who decided it, and when it was needed, together with the agenda and the action register.

Sent to your inbox. Unsubscribe anytime. PDF and Excel: agenda, action register, decision log, and RFI tracker.